Anaerobic Digester #3 Specification W-275
Client| Western Riverside County Regional Wastewater Authority
2021 - 2023 | $6.7 Million
The Work of Project is defined by the Contract Documents and consists of the following:
-
Construction of new concrete digester, complete with fixed steel cover, pump mixing system and all appurtenances including piping, valves, gas safety equipment, instruments and hatches.
-
Installation of new membrane gas holding cover with associated blowers, piping and gas safety equipment.
-
Installation of new digester heating equipment, including pumps and heat exchanger.
-
All other civil, yard piping, mechanical, and electrical work included in the Contract Documents
-
Testing and Startup and Commissioning as described in Section 017500 – Commissioning.
ZTC’s scope of work consisted of witnessing and observing the surface preparation, in-process coating operations, verification of compliance with specification, assessment of repaired coatings, and final visual acceptance and signoff of coatings that were applied to both concrete tank and steel tank cover.